Total Expenses
Batch70 School Project
Renovation of Three-Room School Building
OCNHS
- Construction Materials c/o Calapati General Merchandise (Gene Castro) - PhP 247,927.00
- Roofing and Installation c/o A.R.T. Metal Fabrication (Ador Tan) - PhP 98,000.00
- Jalousies, Frames and Installation c/o Johnlyn Glass Center - PhP 9,000.00
- Vigan Tiles, Pebbles and Installations c/o Olongapo Marble Supply - PhP 80,000.00
- Labor - PhP 129,554.00
- Lighting Fixtures c/o Fumaco, Inc. (30 Sets) - PhP 150,000.00
Grand Total of Expenses = PhP 714,481.00*
*PhP 714,481.00
PhP 350,000.00 - Total Money Raised as of September 30, 2005
PhP 364,481.00 – Outstanding Balance to Date